BIM Execution Plan (BEP) Framework

This BEP framework was developed for a 450,000 sq ft regional hospital project in Texas. It has been anonymized and generalized for use as a reference. The framework covers the minimum requirements that should appear in every project-specific BEP. Actual projects may require additional sections depending on owner requirements, delivery method, and local code constraints.

1. Project Information

Project Name:Regional Medical Center Expansion
Project Size:450,000 sq ft (6 floors + penthouse)
Delivery Method:CM at Risk (GMP)
Coordination Duration:14 weeks (design-assist through MEP rough-in)
BIM Coordinator:MEP Estimation USA (designated senior coordinator)

2. Software & File Standards

Authoring:Autodesk Revit 2024
Federation & Clash Detection:Navisworks Manage 2024
Collaboration:Autodesk BIM 360 / ACC
File Format:Revit .rvt (native); Navisworks .nwf (federated)
Coordinate System:NAD83 State Plane Texas South Central (FIPS 4204), US Survey Foot

3. LOD Responsibility Matrix

Each discipline's model must meet a minimum LOD at each project phase. LOD per AIA G202-2013.

DisciplineSD (Responsible)DD (Responsible)CD/Coordination (Responsible)Fabrication/Install (Responsible)
ArchitecturalLOD 200 (AOR)LOD 300 (AOR)LOD 350 (AOR)LOD 350 (AOR)
StructuralLOD 200 (SOR)LOD 300 (SOR)LOD 350 (SOR)LOD 350 (SOR)
Mechanical (Duct)LOD 200 (MEP)LOD 300 (MEP)LOD 350 (MEP)LOD 400 (Fabricator)
Mechanical (Piping)LOD 200 (MEP)LOD 300 (MEP)LOD 350 (MEP)LOD 400 (Fabricator)
ElectricalLOD 200 (MEP)LOD 300 (MEP)LOD 350 (MEP)LOD 400 (Fabricator)
PlumbingLOD 200 (MEP)LOD 300 (MEP)LOD 350 (MEP)LOD 400 (Fabricator)
Fire ProtectionLOD 200 (MEP)LOD 300 (MEP)LOD 350 (MEP)LOD 400 (Fabricator)
Medical GasLOD 200 (MEP)LOD 300 (MEP)LOD 350 (MEP)LOD 400 (Fabricator)

4. Clash Test Configuration

Selection Set ASelection Set BToleranceTypePriority
DuctworkStructure3"HardP1 - Critical
Piping (all)Structure3"HardP1 - Critical
DuctworkPiping3"HardP2 - High
Electrical (cable tray)Structure3"HardP2 - High
DuctworkElectrical (conduit)6"Soft (clearance)P3 - Medium
PipingElectrical (conduit)6"Soft (clearance)P3 - Medium
Medical GasAll trades3"HardP1 - Critical
EquipmentAll trades12"Soft (access)P2 - High

Note: Our experience across 500+ coordinated projects shows that over-tight clearance tolerances (1-2") increase coordination effort by 30-40% without proportional construction benefit. The 3" hard clash / 6" soft clearance standard balances rigor with practical constructability.

5. Coordination Meeting Schedule

PhaseFrequencyDurationKey Milestone
Model QC (Week 1)Once2 hoursModel Quality Report accepted by all trades
Initial Coordination (Weeks 2-6)Weekly90 minClash count below 500
Detailed Coordination (Weeks 7-11)Weekly90 minClash count below 50
Prefab Gate Review (Week 12)Once2 hoursZero open clashes per zone
Close-Out Review (Week 14)Once1 hourFinal coordinated model + as-built log
Post-Award (ongoing)Monthly60 minField verification updates

6. Prefabrication Gate Criteria

No MEP prefabrication release is authorized until ALL of the following criteria are met for the release zone:

  1. Clash-free: Zero open hard clashes in the release zone. All soft (clearance) clashes documented and trade-accepted.
  2. LOD verified: All system elements in the release zone modeled at minimum LOD 400 (fabrication-level detail including hangers, supports, connections).
  3. Field-verified: Model-to-field accuracy confirmed within 1" for at least 20% of MEP tie-in points in the release zone (laser scan or physical measurement).
  4. Fabricator-ready: Federated model exported to fabricator's native format (SDS/2, CAMduct, TrimPipe) and confirmed compatible by the fabricator.
  5. BEP-compliant: Model file naming, version, and status meet BEP file standard requirements.
  6. Approved: Gate release form signed by GC BIM lead, MEP coordinator, and fabricator representative.

7. Responsibilities Matrix

TaskGCDesign TeamMEP CoordSubs
Model Federation (Navisworks)P-S-
Clash Detection SetupP-S-
Initial Clash Review & Triage--PC
Model Updates (trade-specific)-C-P
Coordination Meeting FacilitationPCSC
Clash Resolution Documentation--PC
As-Built Model Updates--SP

P = Primary / S = Support / C = Collaborate

Source: This BEP framework was developed from direct coordination experience on a 450,000 sq ft healthcare project. Anonymized and generalized for reference. Actual project BEPs should be customized to your specific project delivery method, owner requirements, and trade subcontractor capabilities.

Prepared by James Marchetti, Senior Mechanical Estimator - MEP Estimation USA. James has led mechanical coordination on 14 healthcare projects and has been applying LOD 350-400 coordination workflows since 2015.